Matande CRC

MATANDE CENTRE
The Construction is at an advanced stage.
Preliminary and substructure works have been completed.

Detailed activities done:
TYPE OF WORK       WORK DONE
Preliminary works      100%
Substructure             100%
Super substructure      50%
   

NOTE: The Project is trying to hire a Digital Camera so that pictures of the centre can be sent to you.

Site meetings
• 3 Meetings were conducted in the presence of community members, construction committee and project staff.
• Patrick, Bazwell and Alice attended the Meeting.
• The following were the major outcomes of the meeting:
• Mobilization & registration of Youth for Preschool to be done
• To start teaching under shade while the center is being constructed.
• Strengthen monitoring on usage of construction materials.
• Emphasis was made that the center is for the community and not for an individual as some members were putting it.
• Close monitoring was emphasized to ensure good quality work is achieved.
• The usage of the center was also highlighted such as preschool village meetings, as well as weddings.

Monitoring
Supervisory visits were done to monitor procurement of quality bricks and quality of work done.

Budget
Details of expenditure have been presented. A total of MK191, 842 has been received.

Versyian Hardware Shop
Has suspended the collection of materials due to the remaining balance. The shop attendant has withhold some materials